Wuchuan mercury mine mill operation utilization rate
November 03, 2021
Wuchuan mercury ore mill operation efficiency project unit Best level of history 1984 Annual working day day 288 276 Mill operating rate % 86.9 83.6 Mill utilization % 84.0 74.4 Main reasons for parking and working hours Overhaul, power outage and no mine Parking for 42 days Parking for 54 days Volume utilization factor d/m 3 ·h 0.86 0.82 Hid Bulbs,Hid Headlight Bulbs,H7 Hid Bulb,Hid Headlamps Foshan Kobo Lighting CO.,LTD. , https://www.lightsattack.com