Mine roadway quality inspection and acceptance

        1. Inspection contents of relevant quality control materials during acceptance of roadway engineering
1. Sub-item, divisional engineering acceptance records, visual inspection quality inspection records, and main function project sampling records.
2. Concealed project acceptance records, materials and test block test reports.
3. Raw materials such as cement (including additives, admixtures), steel bars, anchors (including prestressed anchors), supports (including shrinkable brackets), auxiliary materials such as anchors, and materials and specifications of supporting members Information and spot checks.
4. Roadway specification size inspection data, naked roadway specifications and slope inspection data, and gutter specification inspection data.
5. Quality control data for cast-in-place concrete and reinforced concrete, staggered bars, prestressed anchors (anchor cables), shotcrete and supports.
6. Roadway plan and roadway measurement record results.
        Second, the important content of data review and quality inspection during the acceptance of roadway engineering
1. Review of the relevant quality content of cast-in-place concrete and block support; the cast-in-place concrete structure size of cast-in-place concrete and reinforced concrete support, shotcrete support, bracket support, etc. There should be dimensional deviations that affect structural performance and safety (see 1G420075 for details).
2. Review of bolt tightening torque, prestressing of prestressed anchor (anchor cable) after locking, anchor pullout force, concrete strength, and shotcrete strength data.
3. Thickness and deviation of cast-in-place concrete structure, concrete strength inspection (see 1G420075).
4. The total leakage after the completion of the underground diverticulum should meet the requirements of the regulations, see Table 1G420076.



        Third, the important content of the roadway project acceptance and inspection requirements
1. Surface quality inspection of cast-in-place concrete shaft wall (see 1G4Z0075).
2. Waterproof, anti-seepage concrete leakage quality inspection.
3. Inspection of the construction quality requirements of the backfilling of the concrete support structure of the roadway and the backing of the bracket (steel frame) structure.
4. Inspection of the depth of the support column, the laying of the bottom beam, the spacing of the brackets, the deviation of the forward tilting of the horizontal roadway support, and the inspection of the allowable deviation quality requirements of the inclined roadway support.